Sleeper retaining wall calculator

Work out the sleepers, steel posts, bags of concrete, drainage gravel and ag pipe for a sleeper retaining wall, and how deep the posts need to go.

How big is the wall?
m
mm

Sleepers are 200 mm high, so the height is rounded up to whole rows. For an L-shaped wall, do each straight run separately and take one post off for each corner.

Sleepers and posts

Posts go at every sleeper join, so this is also the post spacing. For a 600 mm wall that doesn't need engineering, 2.4 m between posts is the usual limit.

mm
mm

Posts go as deep into the ground as the wall is high, in a hole at least 300 × 300 mm with 100 mm extra at the bottom.

Drainage
mm wide

Ag pipe along the bottom, drainage gravel up to 200 mm from the top, then soil. Use 300 mm or more on clay.

Prices (optional)
$
$
$
$

Starting prices are examples: a 200 × 50 mm, 2.4 m hardwood sleeper and 20 mm blue metal from a Queensland yard's March 2026 price lists, and a 20 kg bag of high-strength concrete at Bunnings. Post prices vary too much to guess, so add yours.

Front view of the wall: sleepers stacked between posts, with the posts set as deep below the ground as the wall is high.600 mm600 mm in the ground

You'll need

9 sleepers

Posts
Concrete
Drainage gravel
Ag pipe
plus the run to an outlet

Check the rules first

Retaining walls hold back a lot of weight, and every state limits how high you can build without approval. Two examples:

  • NSW: a wall can be exempt development if it's no higher than 600 mm and at least 1 m from a boundary, along with other conditions (Wollondilly Shire Council).
  • Queensland: walls over 1 m need building approval, and lower walls can too, for example within 1.5 m of a building or another retaining wall (Moreton Bay City Council).

Rules differ by council and by site, so ring yours before you dig. Higher walls, steep slopes, poor soil, or a driveway or building above the wall can all mean you need an engineer.

How the calculator works it out

  • Rows: standard sleepers are 200 mm high, so wall height ÷ 200, rounded up.
  • Posts: one at every sleeper join, plus one at each end. For a 600 mm wall that doesn't need engineering, 2.4 m between posts is suitable.
  • Post depth: retaining wall posts go half and half, as deep in the ground as the wall is high. So a 600 mm wall needs posts at least 1,200 mm long.
  • Holes: at least 300 × 300 mm, dug an extra 100 mm below the post.
  • Concrete: it takes 110 bags of 20 kg concrete mix to make a cubic metre. The calculator fills the whole hole, which is slightly more than you need once the post is in, so you'll have a little spare.
  • Drainage: ag pipe along the back of the wall at the bottom, then drainage gravel up to 200 mm from the top, finished with soil. That's how the RIDGI concrete sleeper guide does it, with 200 mm left behind the wall for backfill.

Worked example

A straight wall 6 m long and 600 mm high, using 2.4 m sleepers:

  1. 600 ÷ 200 = 3 rows.
  2. 6 ÷ 2.4 = 2.5, so 3 bays: two full sleepers and one cut to 1.2 m in each row. That's 9 sleepers.
  3. 3 bays need 4 posts, each at least 1,200 mm long.
  4. Each hole is 300 × 300 × 700 mm, which is 0.063 m³, or 7 bags of concrete. 4 posts × 7 = 28 bags.
  5. Drainage gravel: 6 m long × 0.2 m wide × 0.4 m high (600 mm less the 200 mm of soil on top) = 0.48 m³.
  6. Ag pipe: 6 m, plus whatever it takes to run it to somewhere the water can go.

Building it

  • Use concrete rated at least 25 MPa in the post holes, as the Galintel post guide specifies.
  • Run a string line and keep every post the same height. Brace them while the concrete sets.
  • Let the concrete cure for a couple of days before you load the posts with sleepers and soil.
  • Cover the gravel with filter fabric before the soil goes on, so the drainage doesn't clog. Run the ag pipe to an outlet (Bunnings Workshop).

Common questions

How many sleepers do I need for a 10 m wall, 400 mm high?

With 2.4 m sleepers: 2 rows of 5 bays, so 10 sleepers and 6 posts. The last bay is 0.4 m, so two sleepers get cut.

How deep should retaining wall posts go?

As deep as the wall is high, plus about 100 mm under the post in the hole.

How many bags of concrete per post?

For a 300 × 300 mm hole, about one bag for every 100 mm of depth. A 700 mm hole takes 7 bags.

Do I need drainage on a small wall?

Yes. Water that builds up behind a wall pushes on it, even on a low wall, and wet soil is much heavier. Ag pipe and gravel are cheap compared to rebuilding.

This calculator is for small garden walls. It doesn't replace an engineer's design, and it can't tell you whether your wall needs approval. Your council can.